The short version
- Concrete volume = length × width × depth, in metres, giving cubic metres (m³).
- For post holes and piers, work out one hole's volume and multiply by the number.
- Add roughly 5–10% for waste, spillage and uneven ground.
- Our calculator does all of it for you.
Order too little concrete and you'll be scrambling mid-pour (and risking a weak cold joint); order way too much and you've paid for concrete you have to dispose of. Getting the volume right is the single most useful bit of maths on any job. Here's how to do it.
Slabs, driveways and footings
For anything rectangular, the formula is simple: length × width × depth, all in metres. So a 4 m × 3 m slab at 100 mm (0.1 m) is 4 × 3 × 0.1 = 1.2 m³. Strip footings are the same idea — length × width × depth — just with a narrow width. Keep everything in metres and you'll get cubic metres out.
Post holes and piers
Round holes use the circle area: π × radius² × depth, then multiply by the number of holes. A 300 mm diameter hole 600 mm deep is about 0.042 m³ each — six of them is roughly 0.25 m³. Square piers are side × side × depth. Fiddly by hand, which is exactly why the calculator has dedicated post-hole and pier tabs.
Always add for waste
Real sites aren't perfect — ground is uneven, there's spillage, and forms flex. Add around 5–10% so you're not caught short. Running out partway through a pour is a genuine problem; being slightly over is cheap insurance by comparison.
Let the tool do the maths. The concrete calculator handles slabs, post holes, footings, piers and bagged mix — with a waste allowance built in. Then we can deliver and pump it. Get a quote →
Over or under — which is safer?
Slightly over beats short every time. A short pour can mean a second delivery (and another short-load fee) or a cold joint that weakens the slab. Big over-ordering wastes money and disposal. Aim for accurate plus a small margin — that's what the waste allowance is for.