Placing concrete into a mesh-reinforced slab with a line pump

The short version

  • Get the prep right — set-out, base, formwork and steel — before any concrete is ordered.
  • Order the correct volume and strength, and line up enough hands (and a pump) for the pour.
  • The pour is time-critical: place, screed, float, edge, then cure.

Pouring a concrete slab isn't complicated, but it is unforgiving — once the truck arrives, the clock's running and concrete waits for no one. The jobs that go smoothly are the ones where the prep was done properly and everyone knew their role. Here's the process the way we run it on Melbourne sites.

1. Set out and prepare the base

Mark out the slab, excavate to depth and get the ground compacted and level. Add and compact your fill, then set the base so the finished slab lands at the right height with the right fall for drainage. Good base prep is what stops a slab cracking or ponding later.

2. Formwork and steel

Set your formwork to the slab's shape and height, braced so it won't move under the weight of wet concrete. Lay reinforcing mesh or bar on chairs so it sits in the correct part of the slab — see our guide to steel mesh size. Add a vapour barrier where required.

3. Order the concrete

Work out the volume with our concrete calculator and order the right mix strength for the job. Book delivery — and a pump if the truck can't reach the slab, which for most backyards it can't.

4. The pour

This is the pressure moment. Place the concrete evenly, screed it off to level, then bull-float to bring up the surface. Once the bleed water's gone, edge and finish (broom, trowel or however the job calls for). Have enough people so no part of the slab is sitting too long — a line or boom pump makes this far calmer by placing concrete exactly where you want it, fast.

5. Cure it

Curing is where slabs are won or lost. Keep the surface moist and protected for the first days so it gains strength properly — see how long a slab takes to cure before you load or build on it.

Doing your own slab? We'll pump it for you so the pour stays under control — and can supply the concrete too. Get a quote →

When to call in a concreter

A shed base or path is a realistic DIY pour with good prep and enough hands. Anything structural, large, or tight on access is better left to a concreter — and whoever pours it, a reliable pump is what keeps the day calm instead of chaotic.

CGI Concrete Pump Melbourne
Written by CJ Iordanou
Co-owner & pump operator, CGI Concrete Pump Melbourne

CJ is one of the two brothers behind CGI Concrete Pump Melbourne. He's spent 15 years in concrete — on the tools laying it and now running the pumps — so these guides come from real Melbourne job sites, not a textbook.

Connect with CJ Iordanou on LinkedIn
Published 31 July 2026
How to Pour a Small Concrete Slab
FAQ

Quick answers

Can I pour a concrete slab myself?
Small slabs like a shed base or path can be a DIY job if you prep properly and have enough hands for the pour — concrete waits for no one. For anything structural, big, or tight on access, get a concreter and a pump. We're happy to talk through your slab before you commit.
What's the hardest part of pouring a slab?
The pour itself, because it's time-critical — once the truck arrives you need to place, screed and finish before it goes off. Good prep and the right gear (a pump for reach and speed) are what keep it calm instead of chaotic.
Concrete pump hire FAQ

More questions about concrete pumping

Which parts of Melbourne and Victoria do you cover?
We hire concrete pumps right across metropolitan Melbourne and out into regional Victoria — including the Mornington Peninsula, Geelong, the Yarra Valley and the outer growth corridors. If you're not sure we reach your site, call us on 0412 845 415.
Can you supply the concrete as well as the pump?
Yes. We can arrange ready-mix supply and delivery alongside the pump so you deal with one team for the whole pour. See our concrete delivery page or ask for a combined quote.
How far ahead should I book a concrete pump?
For most residential jobs a few days' notice secures your preferred date; busy periods and larger commercial pours book out further ahead. The sooner you lock in the date the better — get in touch to check availability.
Do I need a line pump or a boom pump?
It depends on access and pour height. Line pumps suit tight residential sites and ground-level work; boom pumps reach over buildings and into hard-to-access areas. Our line pump vs boom pump guide breaks it down, or we can advise on a quick call.
What should I have ready on site before the pour?
Clear access for the truck, a water source for washout, formwork set and signed off, and enough crew to place and finish. We'll walk you through site setup when you book — see our hire rates for what's included.

Fast quotes · Melbourne & Victoria wide

Book a concrete pump that turns up on time

Tell us the site, the pour and the date. We'll come back with a straight price and a clean, reliable pump crew — line pump or boom, resi or commercial.

📍 Based Kilsyth South VIC — serving all of Melbourne & Victoria
✉
GET A QUOTE — 30 SECONDS